IREN Limited

IRENNasdaqFull coverage

Price
Loading your watchlists

AI-generated

Moatsight's own AI workflow wrote this edition, and Moatsight corrected it before it was published.

  • Written Nov 8, 2026 from 20 sources, including the 10-Q filed Nov 5, 2026.
  • Argued by a bear and a bull critic.

How dossiers are written

Moatsight viewPart 2 of 5 · 13 min read

Business explainer

Loud claims, checked: 2 partly supported · 1 supported · 3 open
VerdictClaimWho and when
Partly supportedThe delay is documented in the 10-Q; how much of Microsoft's spending gap came from IREN is not shownDelays at IREN's Childress site led Microsoft to spend about $5 billion less on capex than planned in its September quarterIn What changedThe Information, November 4, 2026, citing unnamed sources
OpenThe filings neither confirm nor refute the customer accountsCustomers have had extended power outages, network disruption and storage failures at the British Columbia sitesIn What changedSemiAnalysis, October 2026
Partly supportedGrowth is paced by funding; the contracted programme is funded on the company's figuresTighter credit will force most GPU clouds into failure or consolidationIn What changedElon Musk, post on X, October 25, 2026
SupportedFor the data centers only; IREN has $10.0 billion of debt principalIREN's data centers were paid for in cash and carry no debtIn What changedCo-CEO Daniel Roberts, November 5, 2026 earnings call
OpenIREN was not named; its five-year life has held so far in a tight marketAI chips earn for two to three years, so five- and six-year depreciation lives overstate profitsIn What changedMichael Burry, about large cloud companies, as reported by CNBC on November 14, 2025
OpenWhether a pause reaches approvals already granted is not knownA new Texas governor will pause data center approvalsIn What changedGovernor-elect Gina Hinojosa, as reported by The Texas Tribune on November 4, 2026

A verdict is the Moatsight view of what the filings show, not a finding of fact.

The core

IREN is a bitcoin miner that has turned itself, within eighteen months, into an AI cloud: it owns the land, the grid connections and the data centers, buys NVIDIA GPUs, and rents their computing time to Microsoft, NVIDIA, a frontier AI lab and about a dozen AI developers on contracts of three to five years. The economics come down to two numbers per megawatt of IT load: what a customer pays a year for the GPUs housed in it, and what those GPUs and the building cost. On the company's own illustration a megawatt costs about $60 million, and on our cautious arithmetic, which gives the GPUs no value after their first contract, it earns its cost of capital only above about $16 million of revenue a year before tax and overhead, or about $20 million after them; with one more year of GPU use, as our Base scenario assumes, or a large prepayment, the line is lower. Contracts signed in the September quarter were priced at $17 million to $23 million and two signed after it at about $22 million, with 90% of the GPU capex prepaid, and $40 million; the largest, with Microsoft, works out at about $9.7 million. What the business is worth therefore rests on pricing for capacity not yet contracted, on how long GPUs keep earning after their first contract, and on whether IREN can fund about $15 billion of planned spending without diluting its shareholders away.

How IREN makes money

IREN reports two segments (Form 10-Q for the quarter ended September 30, 2026, Note 3):

  • AI Cloud. IREN installs NVIDIA GPU systems in its own data centers and sells their capacity, priced per GPU-hour and fixed for the term of the contract, mostly as reserved capacity for three to five years. Customers range from hyperscalers (Microsoft) and NVIDIA itself to AI developers. Revenue starts only once a deployment is delivered, commissioned and accepted. Since the August 2026 acquisition of Mirantis, IREN also sells software for running these clusters; the 10-Q says Mirantis is not expected to be material to fiscal 2027 revenue.
  • Bitcoin Mining. The original business: mining bitcoin with specialised machines and selling the coins. The machines are being switched off to free power and buildings for GPUs. Installed mining capacity fell from 23.2 EH/s at June 30, 2026 to 7.9 EH/s at September 30, and the 10-Q says the transition should be substantially complete by December 31, 2026, with immaterial mining continuing through calendar 2027.

Inside AI Cloud the income statement shows two lines, which are accounting labels for one business rather than two products (10-Q):

  • AI Cloud Services revenue ($135 million in the first quarter of fiscal 2027) is service revenue under ASC 606, recognised evenly over the contract.
  • AI Cloud Lease revenue ($65 million) arises where a contract, such as Microsoft's, gives the customer control of identified hardware, so it is accounted for as an operating lease under ASC 842. Of the $65 million, $49 million was fixed payments and $16 million was subject to availability conditions (10-Q, Note 4).
Revenue line, USD millionQ1 FY26Q2 FY26Q3 FY26Q4 FY26Q1 FY27
AI Cloud7.317.333.670.5200
Bitcoin Mining233.0167.4111.266.728
Total240.3184.7144.8137.2228
Source: IREN earnings releases of February 5, 2026, May 7, 2026, August 27, 2026 and November 5, 2026; Form 10-Q for the quarter ended September 30, 2026.

The fiscal year ends June 30, so the first quarter of fiscal 2027 is July to September 2026. From that quarter the company rounds to whole millions, which is why the latest column has no decimals.

The customers and the contracts

CustomerWhat is contractedTerms the filings give
MicrosoftFour 50 MW (IT) liquid-cooled deployments ("Horizons 1 to 4") at Childress, Texas; about $9.7 billion over an average five-year term20% of each tranche's contract value paid before delivery, credited against fees after month 24; Horizon 1 accepted in August 2026; Horizons 2 to 4 targeted for the December 2026 quarter
NVIDIAFive-year cloud contract of about $3.4 billion for its internal AI workloads, signed May 2026NVIDIA also holds rights to buy up to 30 million IREN shares at $70, tied to GPU volumes supplied
A frontier AI lab (not named)Multi-year contract signed August 2026, expanded after September 30Value and term not disclosed
AI developersAbout $2.8 billion of multi-year contracts announced July 20, 2026; customers named in the 10-K include Prometheus, Perplexity and Together AIPrepayments of about 45% of GPU capex; weighted average term about four years
Source: Form 10-K for the year ended June 30, 2026; Form 10-Q for the quarter ended September 30, 2026; IREN releases of November 3, 2025 and July 20, 2026; earnings release of November 5, 2026.

The company puts its revenue backlog at $20.3 billion, about two-thirds with investment-grade counterparties (earnings release of November 5, 2026). The 10-Q lets a reader rebuild it: $6,347 million of remaining performance obligations on service contracts plus about $13,957 million of contracted lease value, which includes capacity not yet delivered. The 10-Q expects only $1,529 million of the service obligations to be recognised in the next twelve months. Three customers made up 28%, 24% and 18% of first-quarter revenue; the filings do not name them.

Unit economics of one megawatt. On the November 5, 2026 call, CFO Anthony Lewis walked through an illustration for a liquid-cooled megawatt: about $60 million of capex, one third for the data center and two thirds for GPUs; on a five-year contract at $20 million a year with a prepayment covering half the GPU cost, he said the GPUs pay back in 18 months and the whole investment in about three years. He called it illustrative. We tested it under our own discount rate of 10% (Valuation tab). With an 85% margin on the project (the figure the CFO gave for the Microsoft contract on the November 6, 2025 call), zero value left in the GPUs after the contract, and the building let afterwards at the $130 per kW per month that management said on the November 6, 2025 call it charges its own data centers, one such megawatt is worth about $13.5 million more than it costs. Without the prepayment it is worth $8.7 million more; at $17 million a year, $3.9 million more. The break-even is about $15.8 million a year; after stock-based pay, a share of corporate overhead and a 25% tax it is about $20.2 million (Moatsight calculations). That line is cautious. If the GPUs earn one more year at 45% of the price, as our Base scenario assumes, the break-even after costs is about $19.2 million; with 90% of the GPU cost prepaid it is about $18.4 million. The five-year contract signed after the quarter, at about $22 million per megawatt with 90% of the GPU capex prepaid (earnings release of November 5, 2026), works out on the same arithmetic at about $7.7 million per megawatt above its cost after overhead and tax (Moatsight calculations).

The Microsoft contract sits below that line. $9.7 billion over five years and 200 MW is about $9.7 million per megawatt a year, against GPU purchases of $5.8 billion for the contract (management, November 6, 2025 call), or $29 million per megawatt. On the same method, with a $15 million data center cost, we calculate that the contract is worth about $5.6 million less per megawatt than it costs. That is not how management sees it: on the November 6, 2025 call the CFO put the contract's unlevered return in the low double digits with zero GPU residual value, after a colocation charge, and the levered return at about 25% to 30%. The difference is the discount rate and the value of the building after the term; the point is that the largest contract in the backlog is the thinnest.

How to read this: "ARR" (annualised run-rate revenue) is GPU-hour pricing for GPUs commissioned and under contract, times 8,760 hours. The company's own footnote says it is not GAAP revenue and that "recognized revenue may be materially lower". The CFO said on the November 5, 2026 call that IREN exited September with $1 billion of operating ARR against first-quarter AI Cloud revenue of $200 million, which annualises to $800 million.

The market it sells into

AI computing capacity is sold three ways: by the big clouds (Amazon, Microsoft, Google, Oracle), by specialist GPU clouds such as IREN, and as powered buildings leased to others who install the computers. IREN's 10-K names AWS, Google Cloud, Azure, Oracle, CoreWeave, Nebius, Crusoe, Lambda and Nscale among its competitors and says many have greater resources.

Third-party sizing varies widely with the definition. Analysys Mason, in its 2025 worldwide forecast, put GPU-as-a-service revenue at about $21 billion in 2024, rising to $134 billion in 2030, with inference 78% of it by then. Against that, IREN's operating ARR of $1 billion is under 1% of the 2030 estimate, and its contracted ARR target of more than $4 billion would be about 3%. Growth of the market itself, about 36% a year on that forecast (we calculate), is enough to explain fast growth at IREN without any gain in share; what IREN adds is its own power and buildings, which are scarce.

Management's long-term targets are stated in capacity, not revenue: more than $4 billion of operating ARR by January 2027, possibly February, and 0.8 GW (IT) of data center capacity by the end of calendar 2027 (earnings release of November 5, 2026). The company says it has secured more than 5 GW of power and over 30,000 acres of land, and lists a pipeline of more than 35 GW that it itself calls speculative.

The sites

SitePower, MW (gross)Status at the 10-K and the latest release
Childress, Texas750Operating; Horizon 1 delivered to Microsoft; Horizons 2 to 4 in late-stage construction; air-cooled retrofits under way
Sweetwater 1, Texas1,400Under construction; substation energised April 2026; liquid-cooled build under way
Sweetwater 2, Texas600Under construction (early-stage work)
Kiowa, Oklahoma1,600In development
Mackenzie, British Columbia80Operating AI Cloud (air-cooled); new liquid-cooled halls started on a 100 MW site
Prince George, British Columbia50Operating AI Cloud
Canal Flats, British Columbia30Liquid-cooled deployment planned
Badajoz, Spain300Civil works licence secured (earnings release of November 5, 2026)
Bundey, South Australia800Early-stage development
Source: Form 10-K for the year ended June 30, 2026; earnings release of November 5, 2026.

Operating AI Cloud capacity was about 93 MW at September 30, 2026, against about 40 MW at June 30 (10-Q). The Texas sites carry most of the plan: they hold 2,750 MW, 49.0% of the gross power in the table and 95.5% of the gross power at sites operating or under construction (we calculate). Childress hosts all of Microsoft. At Sweetwater, the release of November 5, 2026 reports the 2 GW hub's "conditional inclusion" in ERCOT's "Batch Zero" process for large connections as base load. On the call that day, Chief Commercial Officer Kent Draper said that Sweetwater 1, the 1.4 GW project, is already connected to the grid, and that the inclusion of Sweetwater 1 and 2 in the base load of the batching process means the 2 GW across the two sites is secured. Only Sweetwater 1 is said to be grid-connected; the condition the release names attaches to the Batch Zero inclusion of the hub as a whole.

What moves the results

DriverEffect on revenueEffect on margin and cash
Megawatts commissioned and acceptedRevenue starts at acceptance, so a month's delay moves a month's revenueDelay credits and service credits are possible under the contracts; costs run regardless
Revenue per megawatt on new contractsRanged from $9.7 million (Microsoft) to $17 million to $23 million (contracts signed in the September quarter, CFO on the November 5 call) and $40 million (a short-term contract signed after the quarter)The level that decides whether new capacity earns its cost (break-even about $15.8 million before tax and overhead, about $20.2 million after with no GPU value after the contract, about $19.2 million with one more year of use)
GPU cost per megawattNoneAbout two thirds of the cost of a megawatt; management said on the August 27, 2026 call that data center and GPU capex requirements would be up about 15% to 20%, with revenue increases expected to outpace them
Customer prepaymentsRecognised over the contract, not when receivedFund part of the GPUs; 45% to 55% on recent contracts, 90% of the GPU capex on the five-year contract signed after the quarter
Life of the GPUs after the first contractOlder H100s were recontracted at double their original price (November 5 release)IREN depreciates GPUs over five years; value beyond that is upside, a shorter life is the main accounting risk
Cost of fundingNoneEffective rates on GPU loans of 7.09% to 7.22% (Microsoft-linked) and 10.38% to 10.70% (GPU Financing 2.0 and 3.0)
Source: Form 10-K for the year ended June 30, 2026; Form 10-Q for the quarter ended September 30, 2026; earnings release of November 5, 2026; IREN earnings calls of August 27 and November 5, 2026.

The cost structure is simple. Cost of revenue for AI Cloud was $28 million in the quarter, 14% of its revenue, mostly staff, power and site costs; the segment's gross margin before depreciation was 86%, as in each of the last four quarters (Earnings tab). Below that sit the large lines: depreciation ($148 million), selling, general and administrative costs ($217 million, of which $106 million was stock-based pay) and interest ($73 million).

Why customers choose IREN, and the moat

The company's case (10-K) is that it owns all three layers (the grid connection and land, the buildings, and the computers and software), so it does not pay a landlord, does not face a landlord's termination rights, and can design the building for the computers. Its grid-connected sites in Texas and British Columbia were secured years ago for bitcoin mining, when power was easy to get; today large connections in Texas go through a queue reviewed by the grid operator and the state, so power already secured is the scarce input. Horizon 1 went from civil works to an NVIDIA "Exemplar Cloud" validated GB300 cluster in about 14 months, co-CEO Daniel Roberts said on the November 5 call. NVIDIA is a customer, a supplier and a prospective shareholder.

What the moat does not include: switching costs for the GPU-hours themselves are low once a contract ends, pricing is set by a competitive market, and the GPUs are bought from the same suppliers everyone uses. The durable part is the power and the buildings; the computers are a commodity that must be bought again every few years.

Honest weaknesses

  • Concentration. Three customers made up 70% of first-quarter revenue, and Microsoft and NVIDIA are what the 10-K calls a substantial majority of contracted revenue. Several other customers are young, privately funded AI companies.
  • The largest contract earns least. Microsoft's $9.7 million per megawatt sits below our break-even, so value creation depends on the newer, smaller contracts.
  • A short record as a cloud operator. IREN has run AI Cloud at scale for about a year. A SemiAnalysis post in October 2026 relayed customer complaints of outages at the British Columbia sites (What changed tab); the filings do not discuss uptime.
  • Capital hunger. Each megawatt costs about $60 million, the GPUs need replacing every few years, and the plan needs far more money than the business generates (Earnings tab).
  • Governance. The two co-CEOs, Daniel and William Roberts, each hold 3.22% of the shares and, mainly through a B class share each, 19.76% of the votes, 39.5% between them (proxy statement of October 13, 2026).

Risks the filings name, in plain words

  • Late delivery. Revenue starts only on acceptance; late delivery can bring delay credits, lost revenue or the right to cancel, while debt costs run (10-K risk factors). The 10-Q says Microsoft-requested changes extend delivery dates without delay credits, but that fees, credits and cost reimbursements are still under discussion.
  • Funding. About $6 billion of the remaining fiscal 2027 plan is not yet funded, and the company may buy GPUs and develop sites before it has the financing or even the customer contracts (10-Q).
  • Technology and prices. GPUs may lose value faster than expected; prices fixed in long contracts do not rise if market prices do (10-K).
  • Texas power rules. Large loads in Texas face new state rules and a verification and audit of all data centers in the connection queue, ordered by the governor on August 3, 2026; the 10-K warns of possible delays in energisation, or changes to energisation levels, at new and existing projects there, including delays in grid connection for the Sweetwater sites. The Texas Tribune reported on November 4, 2026 that the audit was expected to last until December.
  • Guarantees. If Microsoft validly terminates a funded tranche and no new customer is found, IREN guarantees the related debt net of GPU sale proceeds (10-K).
  • Legal. A 2022 securities class action was dismissed with prejudice on February 18, 2026; the plaintiffs' appeal is pending at the Third Circuit. A Canadian tax dispute concerns about $28 million. A US customs claim of about $100 million was resolved in IREN's favour in October 2026 (10-Q).

What we do not know

  • The prices, terms and prepayments of the frontier-lab contract and of the contracts signed after September 30, beyond management's per-megawatt figures.
  • The termination and delay terms of the NVIDIA contract.
  • What residual value IREN assumes for its GPUs; the filings give only the five-year life.
  • How the Microsoft design change will settle between the parties on fees and credits.
  • Uptime and customer retention at the British Columbia sites.
  • Whether the Texas review and the governor-elect's pledged pause on data center approvals reach sites already connected or conditionally approved.

Sources

  1. Earnings release for the quarter ended September 30, 2026 (Form 8-K, exhibit 99.1)IREN LimitedNov 5, 2026
  2. Form 10-Q for the quarter ended September 30, 2026IREN LimitedNov 5, 2026
  3. Form 10-K for the year ended June 30, 2026IREN LimitedAug 27, 2026
  4. Earnings release for fiscal 2026 (Form 8-K, exhibit 99.1)IREN LimitedAug 27, 2026
  5. Earnings release for the quarter ended March 31, 2026 (Form 8-K, exhibit 99.1)IREN LimitedMay 7, 2026
  6. Earnings release for the quarter ended December 31, 2025 (Form 8-K, exhibit 99.1)IREN LimitedFeb 5, 2026
  7. Earnings release for the quarter ended September 30, 2025 (Form 8-K, exhibit 99.1)IREN LimitedNov 6, 2025
  8. Release on the Microsoft AI Cloud contract (Form 8-K, exhibit 99.1)IREN LimitedNov 3, 2025
  9. Release on new AI Cloud contracts and the ARR target (Form 8-K, exhibit 99.1)IREN LimitedJul 20, 2026
  10. Release on the delivery of Horizon 1 (Form 8-K, exhibit 99.1)IREN LimitedAug 13, 2026
  11. Proxy statement for the 2026 annual general meeting (DEF 14A)IREN LimitedOct 13, 2026
  12. Form 4, Daniel Roberts, option sales of September 3 and 4, 2025SEC EDGARSep 5, 2025
  13. Form 4, Daniel Roberts, share sale of September 11, 2025SEC EDGARSep 11, 2025
  14. Form 4, William Roberts, share sale of September 11, 2025SEC EDGARSep 11, 2025
  15. IREN sinks 9% after report links it to Microsoft's AI spending delay https://247wallst.com/investing/2026/11/05/iren-sinks-9-after-report-links-it-to-microsofts-ai-spending-delay-nebius-tumbles-11-coreweave-slides-7/24/7 Wall St.Nov 5, 2026
  16. IREN drops 4% as SemiAnalysis flags its Canadian data centers https://247wallst.com/investing/2026/10/08/iren-drops-4-as-semianalysis-flags-its-canadian-data-centers-core-scientific-pulls-back-2/24/7 Wall St.Oct 8, 2026
  17. Neocloud stocks and Elon Musk's comment on consolidation https://www.cnbc.com/2026/10/26/neocloud-stocks-today-coreweave-nebius-iren-elon-musk.htmlCNBCOct 26, 2026
  18. The question everyone in AI is asking: How long before a GPU depreciates? https://www.cnbc.com/2025/11/14/ai-gpu-depreciation-coreweave-nvidia-michael-burry.htmlCNBCNov 14, 2025
  19. Under Hinojosa, Texas data center approvals could stay paused https://www.texastribune.org/2026/11/04/data-center-texas-pause-gina-hinojosa-governor-policies/The Texas TribuneNov 4, 2026
  20. GPUaaS revenue will reach USD130 billion by 2030 (GPU-as-a-service worldwide forecast 2025-2030) https://www.analysysmason.com/research/content/articles/gpuaas-forecast-overview-rma16/Analysys Mason

General research and analysis by Moatsight, not personalized investment advice. We show, you decide. Disclaimers