Moatsight viewPart 1 of 5 · 4 min read

In brief

Loud claims, checked: 2 partly supported · 1 supported · 3 open
VerdictClaimWho and when
Partly supportedThe delay is documented in the 10-Q; how much of Microsoft's spending gap came from IREN is not shownDelays at IREN's Childress site led Microsoft to spend about $5 billion less on capex than planned in its September quarterIn What changedThe Information, November 4, 2026, citing unnamed sources
OpenThe filings neither confirm nor refute the customer accountsCustomers have had extended power outages, network disruption and storage failures at the British Columbia sitesIn What changedSemiAnalysis, October 2026
Partly supportedGrowth is paced by funding; the contracted programme is funded on the company's figuresTighter credit will force most GPU clouds into failure or consolidationIn What changedElon Musk, post on X, October 25, 2026
SupportedFor the data centers only; IREN has $10.0 billion of debt principalIREN's data centers were paid for in cash and carry no debtIn What changedCo-CEO Daniel Roberts, November 5, 2026 earnings call
OpenIREN was not named; its five-year life has held so far in a tight marketAI chips earn for two to three years, so five- and six-year depreciation lives overstate profitsIn What changedMichael Burry, about large cloud companies, as reported by CNBC on November 14, 2025
OpenWhether a pause reaches approvals already granted is not knownA new Texas governor will pause data center approvalsIn What changedGovernor-elect Gina Hinojosa, as reported by The Texas Tribune on November 4, 2026

A verdict is the Moatsight view of what the filings show, not a finding of fact.

IREN's value turns on two things: whether it can deliver its contracted AI capacity on time at prices that earn more than its capital costs once the GPUs need replacing, and whether it can fund about $15 billion of planned spending without diluting its shareholders away. After the first quarter of fiscal 2027 the evidence is mixed: pricing on new contracts improved, while delivery slipped again and funding got harder. See: What changed › What the quarter changed

The business

IREN was a bitcoin miner and is now an AI cloud. It owns the land, the grid connections and the data centers, buys NVIDIA GPUs, and rents their computing time to Microsoft, NVIDIA, a frontier AI lab and about a dozen AI developers on contracts of three to five years. The company puts its revenue backlog at $20.3 billion, about two-thirds with investment-grade counterparties, and three customers made up 70% of first-quarter revenue. See: Business explainer › The customers and the contracts

What moves results is the megawatts commissioned, the revenue each brings a year, and what the GPUs and buildings cost. On management's illustration a megawatt costs about $60 million. On our cautious arithmetic, which gives the GPUs no value after their first contract, it earns its cost of capital only above about $15.8 million of revenue a year before tax and overhead, or about $20.2 million after them; with one more year of GPU use, as our Base scenario assumes, the line after costs is about $19.2 million. See: Business explainer › What moves the results

The quarter

AI Cloud took over the revenue line. AI Cloud revenue rose from $71 million to $200 million in a quarter as Horizon 1 started billing Microsoft, at an 86% segment gross margin. Total revenue still fell on a year as bitcoin machines were switched off. IREN gives no revenue guidance; its one cost guide, on cash operating expense, was beaten. See: Earnings › The quarter in one table

The cash came from customers, and much of the cost was paid in shares. Operating cash flow of $529 million was less than the $645 million of customer prepayments received in the quarter; without them it was negative. Counting the GPUs, capital spending of $4.8 billion made free cash flow minus $4.3 billion, and net debt rose from $0.2 billion to $4.4 billion in three months. Stock-based pay of $106 million was larger than adjusted EBITDA of $66 million, and shares outstanding rose 43.8% in a year. See: Earnings › Cash: the quarter's real story

Pricing after the quarter was the strongest news. Since September 30, IREN has signed a five-year contract at about $22 million per megawatt with 90% of the GPU capex prepaid by the customer, and a short-term contract at $40 million per megawatt; older H100s at Prince George were recontracted at double their earlier price, the company reported on November 5, 2026. On our arithmetic the five-year contract is worth about $7.7 million per megawatt above its cost after overhead and tax, clearly more than break-even. These are single contracts with unnamed customers: the contracts signed in the September quarter were priced at $17 million to $23 million, and the Microsoft contract works out at about $9.7 million. See: Valuation and projections › Cross-check: what one megawatt is worth

Management's record

Targets IREN controls on its own, such as hashrate, a substation and its own costs, were met or beaten. The dated milestones that depend on Microsoft were late: Horizon 1 arrived about seven and a half months after its first target, and the more than $4 billion ARR target has moved from December 2026 to January, possibly February, 2027. Funding commitments can be taken close to face value; delivery dates should be read with a quarter's margin. See: Earnings › How far management's word can be trusted

What it is worth

We value IREN with a quarterly discounted cash flow on free cash flow after stock-based pay, built block by block of capacity, at a 10% cost of capital. See: Valuation and projections › Method and why it fits

  • Bear (Scenario): $0 per IREN share, probability 25%. New contracts fall back to $16 million per megawatt on four-year terms, and growth stops at committed capacity; the nil comes from these assumptions together, not from the price alone.
  • Base (Scenario): $17.67 per IREN share, probability 60%. New contracts hold at $19 million per megawatt, and the GPUs earn a short tail after their first contract.
  • Bull (Scenario): $125.92 per IREN share, probability 15%. Management's 0.8 GW target is met by December 2027, at $21 million per megawatt. See: Valuation and projections › The scenarios

The probability-weighted value is $29.49 per IREN share (Moatsight est.), and the Bull scenario alone contributes $18.89 of it. The value is most sensitive to what refreshed capacity earns against the cost of new GPUs. At $34 million of GPUs per megawatt, a refreshed megawatt earning $13 million a year leaves the Base value at nil, and one earning $19 million gives $55.30 (Scenario). See: Valuation and projections › Sensitivity

The shares traded at about $21 in early November 2026, which on our Base assumptions corresponds to new contracts at about $19.7 million per megawatt (Moatsight est.). See: Valuation and projections › What today's price implies

What the market is debating

The Information reported on November 4, 2026, citing unnamed sources, that delays at IREN's Childress site led Microsoft to spend about $5 billion less on capex than planned. Our verdict is partly supported: the delay is documented, but who caused how much of the gap is not. See: What changed › What the market is debating

What to watch

  • Horizons 2 to 4 accepted by February 28, 2027. Revenue below $450 million in the March 2027 quarter would mean the ramp is behind our Base.
  • The price of new contracts for the Vera Rubin capacity: $16 million per megawatt or less points to the Bear scenario, above $21 million to the Bull.
  • How the $6 billion is raised. Each billion of equity sold near $21 a share adds about 48 million shares, about 11% of today's count. See: What changed › What to watch

Sources

  1. Earnings release for the quarter ended September 30, 2026 (Form 8-K, exhibit 99.1)IREN LimitedNov 5, 2026
  2. Form 10-Q for the quarter ended September 30, 2026IREN LimitedNov 5, 2026
  3. Form 10-K for the year ended June 30, 2026IREN LimitedAug 27, 2026
  4. Earnings release for fiscal 2026 (Form 8-K, exhibit 99.1)IREN LimitedAug 27, 2026
  5. Earnings release for the quarter ended March 31, 2026 (Form 8-K, exhibit 99.1)IREN LimitedMay 7, 2026
  6. Earnings release for the quarter ended December 31, 2025 (Form 8-K, exhibit 99.1)IREN LimitedFeb 5, 2026
  7. Earnings release for the quarter ended September 30, 2025 (Form 8-K, exhibit 99.1)IREN LimitedNov 6, 2025
  8. Release on the Microsoft AI Cloud contract (Form 8-K, exhibit 99.1)IREN LimitedNov 3, 2025
  9. Release on new AI Cloud contracts and the ARR target (Form 8-K, exhibit 99.1)IREN LimitedJul 20, 2026
  10. Release on the delivery of Horizon 1 (Form 8-K, exhibit 99.1)IREN LimitedAug 13, 2026
  11. Proxy statement for the 2026 annual general meeting (DEF 14A)IREN LimitedOct 13, 2026
  12. Form 4, Daniel Roberts, option sales of September 3 and 4, 2025SEC EDGARSep 5, 2025
  13. Form 4, Daniel Roberts, share sale of September 11, 2025SEC EDGARSep 11, 2025
  14. Form 4, William Roberts, share sale of September 11, 2025SEC EDGARSep 11, 2025
  15. IREN sinks 9% after report links it to Microsoft's AI spending delay https://247wallst.com/investing/2026/11/05/iren-sinks-9-after-report-links-it-to-microsofts-ai-spending-delay-nebius-tumbles-11-coreweave-slides-7/24/7 Wall St.Nov 5, 2026
  16. IREN drops 4% as SemiAnalysis flags its Canadian data centers https://247wallst.com/investing/2026/10/08/iren-drops-4-as-semianalysis-flags-its-canadian-data-centers-core-scientific-pulls-back-2/24/7 Wall St.Oct 8, 2026
  17. Neocloud stocks and Elon Musk's comment on consolidation https://www.cnbc.com/2026/10/26/neocloud-stocks-today-coreweave-nebius-iren-elon-musk.htmlCNBCOct 26, 2026
  18. The question everyone in AI is asking: How long before a GPU depreciates? https://www.cnbc.com/2025/11/14/ai-gpu-depreciation-coreweave-nvidia-michael-burry.htmlCNBCNov 14, 2025
  19. Under Hinojosa, Texas data center approvals could stay paused https://www.texastribune.org/2026/11/04/data-center-texas-pause-gina-hinojosa-governor-policies/The Texas TribuneNov 4, 2026
  20. GPUaaS revenue will reach USD130 billion by 2030 (GPU-as-a-service worldwide forecast 2025-2030) https://www.analysysmason.com/research/content/articles/gpuaas-forecast-overview-rma16/Analysys Mason