CoreWeave, Inc.

CRWVNasdaqFull coverage

Price
Loading your watchlists

AI-generated

Moatsight's own AI workflow wrote this edition, and Moatsight corrected it before it was published.

  • Written Nov 11, 2026 from 20 sources, including the earnings release (8-K) filed Nov 10, 2026.
  • Argued by a bear and a bull critic.

How dossiers are written

Moatsight viewPart 3 of 5 · 20 min read

Earnings

Loud claims, checked: 2 partly supported · 3 open
VerdictClaimWho and when
OpenThe 10-K confirms the six-year life and its sensitivity; no filing shows whether six years is rightLong useful lives for AI servers overstate earnings, and CoreWeave's six-year GPU life is too longIn What changedMichael Burry, post of November 10, 2025 reported by CNBC on November 11, 2025, since applied widely to CoreWeave
Partly supportedSupported for the cost of parent-level unsecured debt; the company still raised convertible notes and a term loan in Q3 2026CoreWeave's funding is breaking down as credit markets tightenIn What changedMarket commentary reported by CNBC on November 6 and November 9, 2026, including Paul Meeks of Freedom Capital Markets
OpenMicrosoft was about 67% of 2025 revenue; existing contracts are take-or-pay with fixed termsMicrosoft's move to fewer neocloud partners threatens CoreWeave's revenueIn What changedCNBC, November 6, 2026, citing people familiar with the matter
OpenMost neocloud providers will not survive as independent companiesIn What changedGartner forecast of October 2026, reported by CNBC on November 4, 2026
Partly supportedPlausible if capex per dollar of revenue is near 2.5 or below; the backlog still needs large capex to deliverContracted cash flows from the backlog will service and repay all of CoreWeave's debtIn What changedCoreWeave's CFO, third-quarter 2026 earnings call, November 10, 2026

A verdict is the Moatsight view of what the filings show, not a finding of fact.

The core

The third quarter of 2026 was CoreWeave's best yet on the measures management targets. Revenue rose 168% year on year to $3,661 million, and adjusted operating margin recovered to 10.4% from 1.0% in the first quarter. Both beat the ranges given on the August 11, 2026 call. The headline still hides the main point for the key question: after depreciation ($1,889 million) and interest ($846 million), the quarter lost $479 million before stock-based compensation and tax, and net loss was $709 million. Cash from operations was positive only because customers prepaid: the $2,127 million inflow from deferred revenue was larger than the whole $1,975 million of operating cash flow. Management has beaten its quarterly revenue and adjusted operating income ranges in eight of ten quarterly rows since the listing. Its record on delivery dates for capacity and capex is weaker.

The quarter against guidance and a year ago

Measure, USD millionQ3 2026Q3 2025ChangeGuidance for Q3 2026 (call, August 11, 2026)Against guidance
Revenue3,6611,365168.2%3,450 to 3,6001.7% above the top
Adjusted operating income37921774.7%200 to 26045.8% above the top
Operating income (GAAP)20752n/anone
Interest expense, net846310172.9%860 to 940below the range
Net loss-709-110n/anone
Diluted EPS, USD per share-1.27-0.22n/anone
Capital expenditures (company definition)14,5111,850n/a11,500 to 13,500above the range
Source: Q3 2026 earnings release of November 10, 2026; Q3 2026 earnings presentation; CoreWeave second-quarter 2026 earnings call, August 11, 2026.

Growth percentages for operating income, net loss and EPS are shown as n/a because the base is small or negative. Interest is compared with the release's Q3 2025 figure of $310 million. The year-ago net loss was flattered by a $127 million tax benefit. The Q3 2026 release says the Q3 2025 tax line included the effect of the One Big Beautiful Bill Act on the first half of 2025.

For the full year 2026, the release raised revenue guidance to $13.0 to $13.3 billion and adjusted operating income guidance to $1.275 to $1.375 billion. Less the nine months reported ($8,314 million of revenue and $528 million of adjusted operating income), this implies a fourth quarter of $4,686 to $4,986 million of revenue and $747 to $847 million of adjusted operating income: a margin of about 16.5% at the midpoints, on our calculation. The release also guides fourth-quarter interest expense to $1.05 to $1.15 billion.

What the headline hides

The trend: margins fell while capacity arrived, and are now recovering

How to show The trend: margins fell while capacity arrived, and are now recovering
QuarterRevenue, USD millionAdjusted operating marginAdjusted EBITDA marginDepreciation and amortisation, % of revenueInterest expense, % of revenueNet loss, USD million
Q1 2025981.616.6%61.7%45.2%26.9%-314.6
Q2 20251,212.816.5%62.1%46.1%22.0%-290.5
Q3 20251,364.715.9%61.4%46.2%22.8%-110.1
Q4 20251,5725.6%57.1%52.2%24.7%-452
Q1 20262,0781.0%55.7%55.2%25.8%-740
Q2 20262,5755.0%58.6%54.1%24.9%-626
Q3 20263,66110.4%61.6%51.6%23.1%-709
Source: Moatsight calculations from the earnings releases of May 14, 2025, August 12, 2025, November 10, 2025, February 26, 2026, May 7, 2026, August 11, 2026 and November 10, 2026.

The pattern fits what management described on the first-quarter 2026 call: new sites run at a loss for a month or two while they are fitted out, and the large deliveries of late 2025 and early 2026 pushed depreciation ahead of revenue. In Q3 2026 revenue caught up. Revenue per dollar of depreciation is still lower than a year ago: $1.94 against $2.16, we calculate. Two forces could explain the gap. One is timing: a record $14.5 billion of equipment was placed in service in the quarter (company capex measure), and it is depreciated from the day it enters service while its revenue ramps over one to two months. The other is that new capacity costs more per dollar of revenue. Equipment still in construction ($9.3 billion, down from $11.9 billion, per the CFO on the call) is not yet depreciated, so it does not explain the gap. The filings do not let us separate the two forces.

Incremental margins: the better test

The change in adjusted operating income divided by the change in revenue, quarter on quarter, shows what each new dollar of revenue earns:

How to show Incremental margins: the better test
QuarterRevenue added, USD millionIncremental adjusted operating margin
Q2 2025231.216.1%
Q3 2025151.911.5%
Q4 2025207.3-62.3%
Q1 2026506-13.2%
Q2 202649721.5%
Q3 20261,08623.1%
Source: Moatsight calculations from the earnings releases listed under the table above.

Two quarters in a row above 20% support management's statement on the first-quarter 2026 call that mature contracts earn contribution margins "in the mid-20s". Measured against the third quarter of 2025, though, the incremental margin is only 7.0%: each extra dollar of revenue over the year brought 7 cents of adjusted operating income, because the trough quarters sit in between. Management's 25% to 30% long-term margin aim (CFO, February 26, 2026 call) needs the recent run to hold.

Adjusted operating income leaves out real costs

Adjusted operating income adds back stock-based compensation ($160 million in Q3 2026, 4.4% of revenue) and the amortisation of acquired intangibles ($12 million). With stock-based compensation counted, the third-quarter margin was 6.0%, not 10.4%. Stock-based compensation has fallen as a share of revenue: 12.3% in 2025, which included IPO-related awards, and 5.7% in the first nine months of 2026.

Adjusted EBITDA ($2,256 million, 62%) also leaves out the two costs that define this business:

How to show Adjusted operating income leaves out real costs
QuarterAdjusted EBITDA less interest, USD millionAdjusted EBITDA less depreciation and interest, USD millionOperating cash flow less cash capex, USD million
Q1 2025342.3-101.2-1,346.2
Q2 2025486.2-73.3-2,704.3
Q3 2025527.5-103.0-1,589.7
Q4 2025510-311-2,501
Q1 2026621-526-4,711
Q2 2026870-523-5,743
Q3 20261,410-479-7,466
Source: Moatsight calculations from the earnings releases listed above.

The CFO's preferred measure is the first column. On the November 10, 2026 call he said EBITDA less interest, excluding the benefit of growing prepayments, should "more than double in 2027". Q3 2026 already shows $1,410 million against $527.5 million a year earlier, up 167.3% on our calculation. The second column is closer to what shareholders earn. It has not been positive in any of the seven quarters. It improved slightly in Q2 2026 and more clearly in Q3 2026.

Cash flow is prepayments

How to read this: operating cash flow of $1,975 million in Q3 2026 includes $2,127 million from the change in deferred revenue (customer prepayments) and is net of a $1,741 million rise in receivables. Without the prepayment line, operating cash flow would have been about $152 million negative, on our calculation. Prepayments are real cash and reduce what CoreWeave must borrow, but they are revenue already paid for: the service still has to be delivered, and the cash will not come again. Cash flow before prepayments is the better gauge of the business's own cash generation.

How to read this: there are two capex figures. Cash purchases of property and equipment were $9,441 million in Q3 2026 and $23,558 million in the first nine months (cash flow statement). The company's own "capital expenditures" figure, which its guidance uses, was $14,511 million and $30,650 million (Q3 2026 earnings presentation). It counts equipment when it enters service: the increase in gross property and equipment ($11,932 million in Q3 2026) less the change in construction in progress (a fall of $2,579 million). Cash capex was 65% of the company's figure in Q3 2026. About half of the $5,070 million gap is construction paid for in earlier quarters that entered service in Q3. The rest is equipment added without a cash payment in the quarter, financed by vendors or accrued as payables. Over the first nine months construction in progress barely changed, and cash capex was 77% of the company's figure. Free cash flow on cash capex understates the investment by roughly that gap.

Free cash flow on the cash definition was minus $20,421 million over the four quarters to Q3 2026, on our calculation: operating cash flow of $7,197 million less cash capex of $27,618 million.

Testing the drivers against history

Interest rates: the volume of debt, not its rate, drives interest. The Q2 2026 10-Q says 100 basis points on floating-rate debt moves interest expense by about $30 million a quarter. Over the past year the rate fell and the bill still rose. The CEO said on the November 10, 2026 call that the weighted-average cost of debt was 7.9%, down 250 basis points year on year. On our calculation, net interest expense ran at an annualised 8.3% of average debt in Q3 2026, against 9.9% in Q3 2025. Net interest expense still rose 172.9%, because total debt rose 234.0%, from $14.0 billion to $46.9 billion. For the equity, how much CoreWeave must borrow matters far more than the rate. The first part of that depends on how much of the build-out customers prepay.

Price: the new driver of 2026. On the November 10, 2026 call the CEO said prices rose about 25% across products in July and "another 10% increase later in the quarter". He also said prices for older Ampere and Hopper GPUs rose 30% to 50% quarter on quarter. In the prospectus supplement for the at-the-market equity program (September 2026), the company said short-dated contracts signed since June 30, 2026 were priced at about $40 million per megawatt per year, for terms of about three to six months. Against that, exit-2026 run-rate revenue guidance of $20 to $21 billion over more than 1.85 GW of active power works out to about $11 million per active megawatt, on our calculation. The prospectus defines its figure as annualised revenue divided by the power needed to serve the clusters, and the company describes active power as critical IT load, so the two are broadly comparable. Short-dated prices are therefore a margin story at the edge, not yet the price of the fleet. The incremental margins above are the first sign that price is reaching the results.

Delivery: the 2025 lesson. The one time a driver failed was physical, not financial. In November 2025 a third-party developer's delay cut the full-year 2025 capex plan from $20 to $23 billion to $12 to $14 billion and trimmed revenue and adjusted operating income guidance. The fourth-quarter 2025 call said the affected deployments were delivered ahead of the revised plan. The record since then is the reverse problem: capex has run above guidance in Q2 and Q3 2026 because deliveries came early.

What management said that is new

  • A profit date. The CFO said on the November 10, 2026 call: "we expect adjusted net loss to reduce meaningfully in 2027 and to become adjusted net income positive in the first half of 2028 and for the full year 2028."
  • A funding pivot. The CFO said that "we do not intend to issue additional parent level unsecured debt through 2027", and that the company expects to raise "less than five billion in incremental parent level capital through 2027". He said 2027 would be funded mainly from customer prepayments, vendor financing and asset-level loans, including a planned investment-grade DDTL at an implied yield of 7% to 7.5%. This replaces the 2025-26 mix of high-yield bonds, convertibles and equity.
  • 2027 capex flat if only the backlog is built. "Should we choose to focus only on our committed backlog, we would expect capex for 2027 to remain in line with our 2026 capex investment while revenue and EBITDA grow significantly" (CFO).
  • Renewals as a free option. The CEO said "more than 130,000 GPUs come off contract in 2027, as do another approximately 170,000 GPUs in 2028". At current prices, he said, the 2027 renewals would add "approaching 4 billion" of annualised revenue with no additional capex. The company says these renewals sit outside the backlog.
  • Demand held back. The CEO said 2028 capacity has not yet been offered to buyers, "because we are waiting for that to season further".

The tone changed. The February 26, 2026 call said that "as we continue to drive down our cost of capital, our dependency on prepayments is reduced". The November call presented prepayments as the main funding source, and cited "recent volatility in the capital markets".

Management track record

Guidance against results

Beat = above the top of the range; Met = inside the range, ends included; Miss = below the bottom of the range; a "more than" target is met only if the actual is at or above it. Each row scores the first guidance given for the period; later changes are in the Note. Scoring is on the number alone, so for interest expense and capital expenditures a Miss means spending below the guided range. Guidance through Q2 2026 was given on the earnings calls; the Q3 2026 release was the first to print it.

Guidance, scored

  1. Q2 2025:Beat · Revenue, USD million; Beat · Adjusted operating income, USD million; Met · Interest expense, USD million; Miss · Capital expenditures, USD million
  2. Q3 2025:Beat · Revenue, USD million; Beat · Adjusted operating income, USD million; Miss · Interest expense, USD million; Miss · Capital expenditures, USD million
  3. FY 2025:Beat · Revenue, USD million; Miss · Adjusted operating income, USD million; Miss · Capital expenditures, USD million; Met · Interest expense, USD million; Miss · Active power at year-end, MW
  4. Q1 2026:Beat · Revenue, USD million; Met · Adjusted operating income, USD million; Met · Interest expense, USD million; Met · Capital expenditures, USD million
  5. Q2 2026:Met · Revenue, USD million; Beat · Adjusted operating income, USD million; Miss · Interest expense, USD million; Beat · Capital expenditures, USD million
  6. Q3 2026:Beat · Revenue, USD million; Beat · Adjusted operating income, USD million; Miss · Interest expense, USD million; Beat · Capital expenditures, USD million
  7. Q4 2026:Due
  8. FY 2026:Due
ScorePeriodMetricGuidanceActualNote
BeatQ2 2025Revenue, USD million1,060 to 1,1001,212.8Given on the May 14, 2025 call
BeatQ2 2025Adjusted operating income, USD million140 to 170199.8
MetQ2 2025Interest expense, USD million260 to 300267.0
MissQ2 2025Capital expenditures, USD million3,000 to 3,5002,900Actual as given on the August 12, 2025 call
BeatQ3 2025Revenue, USD million1,260 to 1,3001,364.7Given on the August 12, 2025 call
BeatQ3 2025Adjusted operating income, USD million160 to 190217.2
MissQ3 2025Interest expense, USD million350 to 390310.6Below the range: lower cost than guided
MissQ3 2025Capital expenditures, USD million2,900 to 3,4001,900Third-party data-centre delay; actual as given on the November 10, 2025 call
BeatFY 2025Revenue, USD million4,900 to 5,1005,131Raised to 5,150 to 5,350 on August 12, 2025; cut to 5,050 to 5,150 on November 10, 2025
MissFY 2025Adjusted operating income, USD million800 to 830666Cut to 690 to 720 on November 10, 2025; the actual was below the cut range too
MissFY 2025Capital expenditures, USD million20,000 to 23,00014,900Cut to 12,000 to 14,000 on November 10, 2025; actual as given on the February 26, 2026 call
MetFY 2025Interest expense, USD million1,210 to 1,2501,229First given on the November 10, 2025 call
MissFY 2025Active power at year-end, MWmore than 900more than 850Cut to more than 850 on November 10, 2025
BeatQ1 2026Revenue, USD million1,900 to 2,0002,078Given on the February 26, 2026 call
MetQ1 2026Adjusted operating income, USD million0 to 4021
MetQ1 2026Interest expense, USD million510 to 590536
MetQ1 2026Capital expenditures, USD million6,000 to 7,0006,800Actual as given on the May 7, 2026 call
MetQ2 2026Revenue, USD million2,450 to 2,6002,575Given on the May 7, 2026 call
BeatQ2 2026Adjusted operating income, USD million30 to 90128
MissQ2 2026Interest expense, USD million650 to 730640Below the range: lower cost than guided
BeatQ2 2026Capital expenditures, USD million7,000 to 9,0009,400Deliveries came early; actual as given on the August 11, 2026 call
BeatQ3 2026Revenue, USD million3,450 to 3,6003,661Given on the August 11, 2026 call
BeatQ3 2026Adjusted operating income, USD million200 to 260379
MissQ3 2026Interest expense, USD million860 to 940846Below the range: lower cost than guided
BeatQ3 2026Capital expenditures, USD million11,500 to 13,50014,511Deliveries pulled forward from Q4
DueQ4 2026Interest expense, USD million1,050 to 1,150In the November 10, 2026 release
DueFY 2026Revenue, USD million12,000 to 13,000Given on February 26, 2026; 12,400 to 13,200 on August 11, 2026; 13,000 to 13,300 in the November 10, 2026 release
DueFY 2026Adjusted operating income, USD million900 to 1,100960 to 1,150 on August 11, 2026; 1,275 to 1,375 in the November 10, 2026 release
DueFY 2026Capital expenditures, USD million30,000 to 35,00031,000 to 35,000 on May 7, 2026; 35,000 to 39,000 on August 11, 2026; 37,000 to 39,000 in the November 10, 2026 release
DueFY 2026Active power at year-end, MWmore than 1,700Raised to more than 1,850 on August 11, 2026; reaffirmed in the November 10, 2026 release
DueFY 2026Annualised run-rate revenue at exit, USD million17,000 to 19,00018,000 to 19,000 on May 7, 2026; 18,500 to 19,500 on August 11, 2026; 20,000 to 21,000 in the November 10, 2026 release

Source: CoreWeave earnings calls of May 14, 2025, August 12, 2025, November 10, 2025, February 26, 2026, May 7, 2026 and August 11, 2026; earnings releases of August 12, 2025, November 10, 2025, February 26, 2026, May 7, 2026, August 11, 2026 and November 10, 2026; Q3 2026 earnings presentation.

The 25 scored rows give 11 Beat, 6 Met and 8 Miss. On revenue and adjusted operating income, the two lines management controls most, the record is nine beats, two met and one miss across 12 rows. The miss is full-year 2025 adjusted operating income, which fell short even of the range cut in November 2025: the fourth-quarter 2025 margin was 5.6% as capacity arrived ahead of revenue. Revenue has never come in below a quarterly range since the listing. The size of the beats points to guidance set with room: the Q3 2026 revenue beat was 1.7% over the top of the range, and the adjusted operating income beat was 45.8%. Three of the eight misses are interest expense below the range, which lowered costs. The other five are delivery: capex and power in 2025, and full-year 2025 adjusted operating income. There is no Q1 2025 row, because the first guidance came on the May 14, 2025 call.

Promise register

StatusPromise, and what became of itFirst madeLater restatements
MissedMore than 900 MW of active power by the end of 2025Cut before the date after a third-party developer's delay; more than 850 MW deliveredQ2 2025 call, August 12, 2025: on track to deliver over 900 megawatts before the end of the yearNovember 10, 2025 call: over 850 MW
MissedFull-year 2025 capex of $20 to $23 billionCut to $12 to $14 billion in November 2025; about $14.9 billion spent, the shortfall moving into 2026Q1 2025 call, May 14, 2025Held on August 12, 2025; cut on November 10, 2025
MetResolve the 2025 data-centre delay within the first quarter of 2026Deliveries made ahead of the November 2025 plan, per the February 2026 call; the customer extended the contract and kept its valueQ3 2025 call, November 10, 2025February 26, 2026 call: delivering the impacted deployments ahead of our Q3 earnings call expectations
DroppedAcquire Core Scientific, adding about 1.3 GW of power and removing more than $10 billion of future lease liabilitiesTerminated on October 30, 2025 after Core Scientific's stockholders did not approve it; no dealAnnounced July 2025; detailed on the August 12, 2025 callNovember 10, 2025 call: the valuation their shareholders required was not a price appropriate for CoreWeave
On trackAdjusted operating margin back to low double digits by Q4 202610.4% reached in Q3 2026, a quarter early; the new full-year guidance implies about 16.5% in Q4Q4 2025 call, February 26, 2026: returning to low-double digit levels by Q4May 7, 2026: same; August 11, 2026: reaching low teens in Q4
RaisedMore than 1.7 GW of active power at the end of 2026Raised to more than 1.85 GW; more than 1.7 GW was already active at September 30, 2026Q4 2025 call, February 26, 2026August 11, 2026 call: more than 1.85 GW; reaffirmed in the November 10, 2026 release
RaisedAnnualised run-rate revenue of $17 to $19 billion at the end of 2026Raised in three steps to $20 to $21 billionQ4 2025 call, February 26, 2026May 7, 2026: $18 to $19 billion; August 11, 2026: $18.5 to $19.5 billion; November 10, 2026 release: $20 to $21 billion
OpenAnnualised run-rate revenue of more than $30 billion at the end of 2027Not due; the end-2026 target is $20 to $21 billionQ4 2025 call, February 26, 2026May 7, 2026 call: more than 75% already contracted; November 10, 2026 call: expects to meaningfully exceed it
Quietly reframedBring the contracted power base online by the end of 2027Wording softened from virtually all of 3.1 GW to a substantial majority; active power was more than 1.7 GW against more than 4.6 GW contracted at September 30, 2026Q4 2025 call, February 26, 2026: virtually all of 3.1 GW contracted to come online by the end of 2027May 7, 2026 call: substantial majority by the end of 2027
OpenLong-term adjusted operating margin of 25% to 30%No date given; 6.4% in the first nine months of 2026Q4 2025 call, February 26, 2026: confident in our ability to achieve 25% to 30% margins over the long termNot restated in these terms on the May, August or November 2026 calls
OpenAt least 8 GW of active power by 2030More than 1.7 GW active and more than 4.6 GW contracted at September 30, 2026Q4 2025 call, February 26, 2026: more than 5 GW beyond the contracted footprint by 2030May 7, 2026: more than 8 GW by 2030; August 11, 2026: at least 8 GW
OpenCost of debt on a path to investment gradeOne secured facility (DDTL 4.0) carries an investment-grade rating; the weighted cost of debt was 7.9%, but parent bonds yielded above 16% in November 2026 (CNBC)Q4 2025 call, February 26, 2026: staying on our targeted path to reach investment gradeMay 7, 2026: our stated goal of driving our cost of debt to investment-grade
On trackManaged-inference annualised revenue of at least $250 million by the end of 2026More than $250 million of booked annualised revenue, per the November 10, 2026 callQ2 2026 call, August 11, 2026
OpenFirst self-built data centre (Kenilworth, New Jersey) online in 2026Not reported as online by November 10, 2026Q2 2025 call, August 12, 2025: initial phase in 2026May 7 and August 11, 2026: later this year
OpenAbout $9 billion of customer prepayments and deposits in the three months after September 30, 2026Not dueQ3 2026 release, November 10, 2026
OpenNo new parent-level unsecured debt, and less than $5 billion of parent-level capital, through 2027Not dueQ3 2026 call, November 10, 2026
OpenAdjusted net income positive in the first half of 2028 and for full-year 2028Not due; adjusted net loss was $529 million in Q3 2026Q3 2026 call, November 10, 2026
What the ten status words mean
Met
Done as promised, by the date given.
Exceeded
Done, and more than promised.
On track
Not due yet; the latest figures point to it.
Open
Not due yet, and the figures so far cannot settle it.
Slipped
Not done by the date given, and still pursued.
Lowered
Cut openly before its date; the new target is in "What became of it".
Raised
Lifted openly before its date; the new target is in "What became of it".
Quietly reframed
Changed without being called a change.
Dropped
No longer pursued or mentioned.
Missed
Due, and not delivered.

Source: CoreWeave earnings calls of May 14, 2025, August 12, 2025, November 10, 2025, February 26, 2026, May 7, 2026, August 11, 2026 and November 10, 2026; Q3 2026 earnings release of November 10, 2026; CNBC, November 6, 2026.

The register leaves out smaller product launches and the international sites (Spain, the United Kingdom, India and Indonesia), which have no dated targets to score.

When a target slipped

The 2025 miss had a single cause, and management named it at once. On the November 10, 2025 call the CEO said the shortfall came from "temporary delays related to a third-party data center developer, who is behind schedule", at the powered-shell level. The affected customer agreed to move the delivery schedule and extend the contract's end date, keeping its total value. The company cut capex, power and margin guidance on the same day, rather than in stages. By the February 26, 2026 call the deployments had been delivered. The cost was real: full-year 2025 adjusted operating income of $666 million against an initial $800 to $830 million. The cause was a supplier, not demand. Since then, single-developer risk has been addressed in words: on the first-quarter 2026 call management said no data-centre provider delivered more than 17% of active infrastructure. A securities class action filed in January 2026, which the company says is without merit, concerns this period.

Capital allocation

CoreWeave has bought back no shares and paid no common dividends; treasury stock is unchanged at $34 million. Capital has gone one way, into the build-out, and has been raised in every form available:

RaiseDateSizePrice or conversion price, USD per share
IPO, Class A sharesMarch 2025about $1.4 billion net40.00
Private placement to NVIDIAJanuary 2026$2.0 billion87.20
Private placement (Jane Street)April 2026about $1.0 billion109.00
1.75% convertible notes due 2032April 2026$4.0 billionabout 119.60
2.875% convertible notes due 2033September 2026$4.2 billionabout 97.85
At-the-market equity programSeptember 2026up to 35 million sharesmarket
Source: Form 10-K for the year ended December 31, 2025; Form 10-Q for the quarter ended June 30, 2026; Form 8-K of September 22, 2026; Q3 2026 earnings release of November 10, 2026.

Equity was sold well for existing holders: the November 10, 2026 close of $48.73 per share was 44% below the NVIDIA placement price and 55% below the Jane Street price, on our calculation. The convertible notes carry low coupons, but the conversion price fell between the April and September issues, and the capped calls bought to limit dilution cost $1,058 million in the first nine months of 2026. Debt rose from $21.4 billion at the end of 2025 to $46.9 billion at September 30, 2026: $27,048 million borrowed and $7,563 million repaid in nine months. Acquisitions have been small next to this. The largest was Weights & Biases, for about $1.03 billion. The Core Scientific purchase, the one attempt at a large deal, failed.

Insiders

Form 4 filings over the past year show repeated sales by all three co-founders (Michael Intrator, Brian Venturo and Brannin McBee) and by other officers. Most were made under Rule 10b5-1 trading plans, which the 10-K lists. One example: Mr. Venturo adopted a plan on November 13, 2025 covering about 7.4 million shares, active from April 1 to December 31, 2026. Some sales are only to cover tax on vesting shares. The Form 4 filed on November 10, 2026 shows the chief operating officer selling 13,611 shares at $46.23 per share for that purpose. We found no open-market purchases by officers or directors. Pre-arranged sales by founders who hold most of the votes say little about their view of value, but they add a steady supply of shares, and they have continued through the price fall.

How far management's word can be trusted

On the numbers it sets for the next quarter, management's word is good and conservative: revenue has never come in below a quarterly range, and the size of the beats suggests ranges set with room. On physical delivery and on long-range aims, its word is less reliable. The 2025 power and capex targets were missed. The wording on bringing contracted power online softened within a quarter. The aim of a falling cost of capital has met a credit market that, in November 2026, priced the parent's bonds above 16%. The new promises of November 2026 are dated and checkable: EBITDA less interest more than doubling in 2027, no new parent unsecured debt through 2027, and adjusted net income in the first half of 2028. They are the ones to hold management to.

Sources

  1. Q3 2026 earnings release (Form 8-K, exhibit 99.1), November 10, 2026CoreWeave, Inc.Nov 10, 2026
  2. Q3 2026 earnings presentationCoreWeave, Inc.Nov 10, 2026
  3. Q4 and FY 2026 outlook presentationCoreWeave, Inc.Nov 10, 2026
  4. Form 10-K for the year ended December 31, 2025CoreWeave, Inc.Mar 2, 2026
  5. Form 10-Q for the quarter ended June 30, 2026CoreWeave, Inc.Aug 12, 2026
  6. Form 8-K of September 22, 2026 (2.875% convertible senior notes due 2033)CoreWeave, Inc.Sep 22, 2026
  7. Prospectus supplement (Form 424B5) for the at-the-market equity program, September 2026CoreWeave, Inc.Sep 17, 2026
  8. Earnings release for the second quarter of 2026, August 11, 2026CoreWeave, Inc.Aug 11, 2026
  9. Earnings release for the first quarter of 2026, May 7, 2026CoreWeave, Inc.May 7, 2026
  10. Earnings release for the fourth quarter and fiscal year 2025, February 26, 2026CoreWeave, Inc.Feb 26, 2026
  11. Earnings release for the third quarter of 2025, November 10, 2025CoreWeave, Inc.Nov 10, 2025
  12. Earnings release for the second quarter of 2025, August 12, 2025CoreWeave, Inc.Aug 12, 2025
  13. Earnings release for the first quarter of 2025, May 14, 2025CoreWeave, Inc.May 14, 2025
  14. Form 4 filed November 10, 2026 (chief operating officer)CoreWeave, Inc.Nov 10, 2026
  15. Neocloud Market Forecast to Approach $400B by 2031, Driven by Surging AI Infrastructure Demand https://www.srgresearch.com/articles/neocloud-market-forecast-to-approach-400b-by-2031-driven-by-surging-ai-infrastructure-demandSynergy Research GroupApr 2, 2026
  16. 'Big Short' investor Michael Burry accuses AI hyperscalers of artificially boosting earnings https://www.cnbc.com/2025/11/11/big-short-investor-michael-burry-accuses-ai-hyperscalers-of-artificially-boosting-earnings.htmlCNBCNov 11, 2025
  17. Democrats may go after data centers. That's not a reason to dump all your AI stocks https://cnbc.com/2026/11/04/democratic-data-center-pushback-could-help-ai-stocks.htmlCNBCNov 4, 2026
  18. The AI 'credit card' is getting costlier as CoreWeave bond yield tops 16% https://www.cnbc.com/2026/11/06/coreweave-bond-yield-tops-16percent-as-ai-credit-stress-rises.htmlCNBCNov 6, 2026
  19. Microsoft plans to use fewer neoclouds as AI buildout shows signs of strain https://www.cnbc.com/2026/11/06/microsoft-moves-to-consolidate-its-relationships-with-neoclouds-in-ai.htmlCNBCNov 6, 2026
  20. CoreWeave confronts 'doom cycle' narrative as neocloud credit risk overshadows growth https://www.cnbc.com/2026/11/09/coreweave-debt-credit-risk-neoclouds.htmlCNBCNov 9, 2026

General research and analysis by Moatsight, not personalized investment advice. We show, you decide. Disclaimers